Metered electricity.
Delivered kWh × an agreed tariff. Set service level, response, billing, escalation and contract term.
Sunroof / Project room / 19 October 2026
The route to our first paying customer: validate demand, agree a viable electricity service, fund the installation and prove daily operation.
Measure one agreed load.
Study + proposal. No solar plant.
Customer and quotes unconfirmed.
Start with a defined routine load at a private hospital or hotel in Greater Banjul. Measure demand, compare the customer’s existing energy costs and build an offer they will accept. Only repeat the configuration once operation and capital recovery are credible.
Delivered kWh × an agreed tariff. Set service level, response, billing, escalation and contract term.
Financing, qualified installation, monitoring, maintenance, repairs and separately agreed capacity upgrades.
Grid energy, generator fuel, major roof works and clinical UPS are explicitly scoped. No unapproved export income.
Can one measured load support a customer-accepted tariff that pays for the service and the capital?
A customer can buy a system from local installers. Compare our lifetime delivered cost with that ownership option.
Greenlink already publishes lease references. Our proposed advantage is accountable metered delivery, transparent billing and dependable local support — still to be demonstrated.
A better grid reduces the value of our backup. Measure avoidable fuel, maintenance and interrupted work rather than count every existing cost as a saving.
Greenlink’s published Gambian project referencesLease and installed-project evidence rechecked 19 October 2026. Customer-specific asset and contract status remains unverified.
PURA’s 2023 determined rates, still displayed when checked 19 October 2026. Verify the actual bill, meter class and any later tariff decision before pricing. These are grid benchmarks, not Sunroof prices or savings. PURA source.
Each step ends in a decision. Founder responsibilities coordinate the work; qualified specialists perform the required design, safety and legal checks.
Arrange three site conversations, collect bills and select one suitable site. Confirm whether it uses an existing roof or needs a new roof/canopy. Coordinate the electrician, roof survey and 14-day load recording.
With qualified designers, check demand, roof/foundation constraints and grid/generator boundaries. Identify which proposed platform variants could fit.
Check the electricity buyer, payment route, current costs and a preliminary service offer.
A measured load, a named buyer, a roof route and a clear service boundary.
Price local mounting or a new roof structure with qualified partners. Check fabrication, transport, installation, spares and service availability.
Lead the first configuration library: compatible PV, battery, inverter/control families, permitted capacity steps and roof variants. Prepare a repeatable bill of materials, drawings and acceptance tests; qualify site-specific changes.
Build a configuration-based price catalogue and complete cash plan. Separate new-roof and platform-development costs. Confirm funding, approval requirements and a customer-reviewed kWh offer.
One qualified reference configuration, a fully quoted cash plan and an agreed electricity offer.
Prepare installation logistics and the local team. Record assembly steps, local supply sources and training so the next site can reuse the process.
Qualified specialists install and commission the reference system. Verify all operating/protection modes; record as-built changes and complete the reusable handover, test and maintenance package.
Secure funding and the customer agreement before ordering. Agree metering, tariff, invoicing, service response and insurance.
An accepted reference installation, required permissions and a documented package for repeat delivery.
Run local service with a shared checklist and spare-parts list. Track site issues, maintain customer contact and train the local team.
Review measured operation and revise the configuration library. Expand only with compatible modules inside qualified capacity, roof and connection limits.
Track collections, full operating costs, reserves and capital recovery. Compare repeat-site economics; approve the next configuration only from measured results and complete quotes.
A proven reference service and a documented, costed route to the next site.
Visit three prospects. Rent a calibrated logger for 14 days at one qualified site. A qualified electrician installs it; an engineer interprets the result. No panels, battery or generator are bought.
$1,670 costs + $334 reserve + $250 refundable deposit.
| Input | USD |
|---|---|
| Energy logger rental · 2 weeks | $360 |
| Qualified electrician visits | $200 |
| Customer / site visits | $120 |
| Independent engineering analysis | $400 |
| Local field support | $140 |
| Data + printing | $30 |
| Initial tariff / contract review | $150 |
| Local travel + consumables | $120 |
| Provisional local taxes / permissions | $150 |
| Test-cost subtotal | $1,670 |
| 20% contingency | $334 |
| Refundable deposit · liquidity | $250 |
| Total cash required | $2,254 |
The deposit is cash tied up, not an immediate expense. No sales, resale or assumed refund is deducted. All local prices and permission/tax allowances require written offers. Founders’ time is unpaid; founder pay and travel are excluded.
A measured load profile, a common specification for comparable quotes, and a customer-reviewed kWh offer. It does not prove installed-system performance or uninterrupted supply.
The $360 logger line is an allowance anchored to a dated UK hire benchmark, not an offer delivered to The Gambia. Confirm calibration, local availability, rental rights, transport and deposit terms before booking.
Reconcile study costs with later engineering provisions. Do not mechanically add the validation and deployment budgets.
Choose a qualified platform configuration, then adapt its capacity and roof interface to the site. A safe, billable service still needs site rights, commissioning and a local operating team.
Build the first project as a reference configuration for the next. Select compatible capacity blocks and an approved roof variant; reuse the engineering package, operating process and spare-parts logic.
Qualified component families, control and metering interfaces, drawings, commissioning tests, monitoring, billing, maintenance and training.
PV and storage capacity, mounting or new-roof variant, layout, cable routes and compatible grid/generator connections.
Demand, roof condition or foundations, wind/structural loads, corrosion exposure, drainage, electrical protection, connection rules and permits.
Joachim leads the technical configuration library with qualified designers; Lamin tests local buildability, roof supply and installation; Dominik defines configuration pricing, funding, service terms and repeat economics.
Platform development is part of the first-project brief, not an existing certified product. Standardisation is intended to simplify repeat delivery; installation time, cost reductions and unlimited expansion are not claimed.
Inherited sizing hypothesis, not a customer design. Measure demand first. Nominal storage is not usable AC energy or guaranteed backup duration.
Count illustration: 40 × 500 Wp = 20 kWp. No module model or supplier is selected. Confirm shading, usable roof, layout, yield, module certificates, hot-weather output and local warranty support. Actual string design and module count belong in the installer’s quotation. Select a qualified module family that can be reused in the platform; define permitted array/string increments and the inverter/roof limits before expansion.
Existing roof: survey condition and structure, then select a qualified mounting variant with suitable rails/fixings, corrosion protection, roof seals, safe access and installation-at-height arrangements. New roof/canopy: qualified partners must design and quote structure, foundations, weatherproof covering, drainage and PV mounting together. Panels alone are not assumed watertight. Reuse approved variants where suitable; verify local structural/wind exposure at every site. New structures and major repairs are outside the existing-roof reference allowance.
Illustrative LiFePO4 format: 8 × 5.12 kWh = 40.96 kWh nominal. No battery model or supplier is selected. Include a compatible battery-management system, cabinet/rack, battery disconnects/protection and temperature/environment provisions. Usable AC energy is lower and depends on operating reserve, losses and ageing. Choose capacity from required duty; storage can be reduced if the measured service does not need it. Specify permitted battery increments, compatible inverter/BMS combinations and operating limits; later additions require technical approval.
Select suitable inverter/charger equipment and the solar conversion path: integrated MPPT, separate MPPT chargers or an AC-coupled PV inverter, as designed. Avoid double-counting integrated functions. Phase count, continuous/peak kW or kVA and charge limits follow measured loads and the battery; 20 kWp of panels does not specify inverter output.
Include rated cables/connectors, containment, distribution boards, isolators, fuses/breakers, designed surge protection, earthing/bonding and any required lightning/fire provisions. The designer specifies ratings and quantities from routes, fault conditions, equipment and applicable rules. No generic component basket substitutes for the protection design.
Define the customer delivery boundary and an accepted billing meter, calibration/verification and readings. Measure grid and generator contributions where needed to allocate costs; a controller’s monitoring meter is not automatically a lawful revenue meter. Agree tariff, source-energy/fuel treatment and invoice checks.
A compatible EMS/controller, required communication cables and a site-appropriate internet/data plan. Configure monitoring, local records when offline, alerts, permissions and backups. Start with standard tools and a simple invoice/maintenance ledger; a custom platform is not required for site one. Reuse one qualified control/metering interface and commissioning template across configurations.
Assess the existing connection, protection, metering and transfer/maintenance-bypass arrangement. Obtain the applicable NAWEC/PURA requirements, including anti-islanding and permitted operating mode. Surplus can serve suitable on-site demand or charge storage; when neither is possible, curtail. Export only under an approved technical and commercial arrangement.
Survey the actual generator, controls, service condition, phase/rating and fuel responsibility. Specify compatible transfer/interlocking, input limits, start/stop integration if supported and maintenance bypass with the qualified team. A dual-input inverter is one possible architecture, not a selected model. The reference budget excludes a new generator and its fuel.
Include engineering, installation/lifting, independent checks as needed, commissioning, as-built drawings, test records, operator training, warranties and initial spares. Agree cleaning/inspection, fault response, local technician access and replacement reserve. Acceptance must test actual grid, storage, generator, metering and protection modes. Reuse the reference installation checklist, training package, documentation format and spare-parts list, recording any approved site-specific changes.
Theatre, ICU, medical UPS and clinical redundancy need a separate qualified design. Payment disputes must not lead to improvised disconnection of clinical circuits.
GAM-Solar and Shyben are existing enquiry routes for installation and generator expertise, not selected providers. Local legal, electrical, structural, metering and insurance specialists must qualify the final scope.
Fifteen researched prospects from the Gambia work. Begin with Sharab, Africmed and African Princess to compare one defined routine load. Check current assets, contracts, decision authority and payment capacity before proposing a system.
Research leads, not customers, partners or confirmed demand. Prospect evidence retains its 15–16 October observation dates. Africmed services and African Princess room inventory were rechecked 19 October; Sharab’s direct page timed out in that recheck.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Research prospect · no customer interest or energy gap confirmed.
Industrial prospects belong to a later dedicated case. Room counts, historical factory capacity and advertised services are not measured electricity loads.
The existing $63,000 case assumes an existing roof; it does not fund the new-roof route. Add the complete roof/structure cost and recompute the tariff before offering that option. Platform-development costs also need to be quoted; no standardisation savings are deducted.
Inherited planning model, not quotations or a customer offer. The storage-inclusive case is operating-cash positive, but does not recover its stated ten-year capital target at the assumed $0.28/kWh tariff.
Prove the customer benefit and collected tariff before funding equipment. More battery is not automatically a better business.
After operation + reserve, before tax.
1,500 yield · 70% sold · $0.22/kWhAfter operation + reserve, before tax.
1,650 yield · 85% sold · $0.28/kWhAfter operation + reserve, before tax.
1,750 yield · 92% sold · $0.32/kWhIllustrative annual-yield equivalent months, not a seasonal cash forecast. USD, before tax, founder pay/travel and debt service. Sold share combines losses, curtailment and demand matching.
| Scope | Range | Selected |
|---|---|---|
| PV, mounting + DC works | $7–11k | $9,000 |
| Battery equipment | $14–22k | $18,000 |
| Conversion, controls + protection | $6–10k | $8,000 |
| Installation + existing generator interface | $5–9k | $6,500 |
| Freight, clearance + provisional taxes | $4–8k | $6,000 |
| Engineering, permits + agreement | $2–4k | $3,000 |
| Deployment contingency | $4–8k | $6,500 |
| Deployment | $42–72k | $57,000 |
| Liquidity | $4–10k | $6,000 |
| Combined funding | $46–82k | $63,000 |
Outside scope: a new roof or canopy (including structure, foundations and weatherproofing), land, major roof repairs, new generator, fuel stock, clinical UPS/redundancy, founder pay/travel and a second site. Provisional clearance/tax allowances need product classification and a broker/accountant. No tax exemption is assumed. Recoverable VAT can still create a cash-timing gap.
20 kWp × 1,650 kWh/kWp/year × 85% sold ÷ 12
= 2,337.5 delivered solar kWh / month
Covers operation + reserve. Does not recover installation.
Adds ten-year recovery of $57,000 at a 10% hurdle. Liquidity separate.
Capital tariff = variable cost + (monthly fixed costs + reserve + capital-recovery charge) ÷ delivered kWh. The annual capital-recovery factor is r ÷ [1 − (1 + r)−n].
Lower the sold share, raise replacement costs and compare smaller storage. Stress a 15% GMD depreciation against USD equipment and delayed customer payment. Indexation is a negotiation and affordability issue, not an assumed right.
Grid purchases and generator fuel are outside this solar-only model. Meter and allocate them separately or add their full costs. No export, subsidy or uncommitted funding receipts are assumed.
The original Gambia detail informed this project room. Data is dated, prospects are uncontacted and allowances need quotes. No contract, licence, partner capacity or saving is represented as secured.
Advertises 141 rooms/suites with air conditioning and mini-fridges. This is not measured occupancy, electricity demand or willingness to buy.
Figure 2.7 places The Gambia among countries with high reported outage incidence. The figure uses 2023/24 Enterprise Survey estimates; it is not a current outage forecast or a survey of our prospects. No exact chart-derived percentage is promoted in the short reading layer.
Published commercial and hotel/industry rates are GMD 14.90 and 15.90/kWh. Use the actual customer bill and check for later decisions before pricing.
Obtain the applicable site-specific generation, supply and grid-connection requirements. Calling electricity a service does not itself remove licensing obligations.
Publishes Gambian commercial projects, including lease references. Existing assets, dates and contract status must be checked; financing alone is not an unoccupied market.
Illustrates inverter/charger, batteries, controller, meters and alternative AC/DC solar coupling. A manufacturer architecture example, not our selected hardware or Gambian approval.
Relates storage and inverter sizing to system duty and expected loads; addresses anti-islanding. Does not size our site or establish local grid-code acceptance.
Includes a 51.2 V / 100 Ah, 5.12 kWh LiFePO4 format and BMS requirements. Eight such nominal units illustrate 40.96 kWh, not usable AC energy, a selected battery bank or a complete offer.
Example of local/remote system monitoring, compatible device integration and offline data storage. Our connectivity, alert escalation, permissions and billing integration still need configuration.
Shows one architecture accepting two AC sources and multi-phase arrangements. Not a selected unit, generator rating, wiring design or clinical continuity guarantee.
Supports rated wiring, fusing and electrical-safety scoping. The site designer must specify actual protection, earthing, cable routes and ratings; no installation instructions are provided here.
Supports structural/electrical assessment, roof condition and safe installation planning. This is a technical checklist reference, not Gambian building/electrical law.
Describes checking supply, storage, metering and generator operation. A qualified team must define and witness site-specific acceptance tests.
Historical technical reference for documentation, maintenance and service scope, not a current Gambian service price or local regulatory approval.
Identifies the electricity regulatory framework and NAWEC’s role. Local counsel, PURA and NAWEC must establish the applicable generation/supply, metering, grid and export route for the proposed site; no threshold or exemption inferred.
Illustrates families of mounting solutions for different roof types. This supports the platform concept, not a selected supplier, a local approval or a new-roof structural design.
Site-specific generation, supply, metering and export requirements must be confirmed. Calling electricity a service does not remove licensing requirements.
£19/day, 14 days £266 ex VAT, approximately $352 at the dated cross-rate. No Gambia delivery, overseas-hire permission or local availability is established.
Replace indicative historical cross-rates with the actual dealing rate when comparing current quotations.
Preserved independently. Legacy fixed-monthly plans, licensing workarounds, assumed savings and unrelated ventures are not adopted by Sunroof.
Architectural concept images include AI-generated illustrations; diagrams and the modular product film are original explanatory work. They do not depict installed Sunroof projects. Team photographs are supplied real images. Fonts: Manrope and DM Mono; licences included locally.
Before ordering equipment
Approved design. Agreed customer. Complete funding.
Then install, commission and prove the service.